Production OEE Calculator

Free · No sign-up

Combine availability, performance and quality to assess a production period.

Your inputs

minutes
minutes
minutes
units
units

Example values are shown. Edit them for your calculation.

Results update automatically as you edit.

Inputs stay in this page. No account needed.

Your result

FINANCIAL

Example values are prefilled. Results update automatically when JavaScript is available.

What this tool calculates

Combine availability, performance and quality to assess a production period.

Inputs used: Planned production time, Actual run time, Ideal cycle time per unit, Total units produced, Good units produced.

On this page How it works & practical examples

How to use the Production OEE Calculator

Use one production period and consistent time units. Availability excludes downtime, performance compares actual throughput with the entered ideal cycle, and quality measures the good-unit share.

The calculation

OEE = (run/planned) × (ideal cycle × total/run) × (good/total)

Worked example

480 planned minutes, 420 run minutes, 0.5 ideal minutes per unit, 700 total and 665 good units give 69.2708% OEE.

Assumptions and limits

Requires positive run time, run time no greater than planned time, good units no greater than total units, and an ideal production time no greater than actual run time. No industry target is prescribed.